Refrigerant leak repair verification tests: what the rule says

As of Nov 8, 2026

After a leak repair, 40 CFR 84.106(e) asks for two tests: an initial one and a follow-up one. This page quotes both, with their time limits and the records paragraph. It does not say whether the rule applies to your appliances. Rules can change; check eCFR and EPA.

The two tests at a glance

Verification tests in 84.106(e), as of Nov 8, 2026
TestWhen the rule text saysWhat it must showSection
Initial“within 30 days (or 120 days if an industrial process shutdown is required) of a refrigerant-containing appliance exceeding the applicable leak rate”, “Unless granted additional time”“the adjustments or alterations to the refrigerant-containing appliance have held”84.106(e)(1)
Follow-up“within 10 days of the successful initial verification test or 10 days of the refrigerant-containing appliance reaching normal operating characteristics and conditions (if the refrigerant-containing appliance or isolated component was evacuated for the repair(s))”“that leaks where repair attempts were made are repaired”84.106(e)(2)(i)

Rules can change; check eCFR and EPA.

The initial test, and when it happens

“The owner or operator must conduct both initial and follow-up verification tests on each leak that was repaired under paragraph (d) of this section.”

84.106(e)

For the initial test, the rule text separates two cases:

  • Repairs that can be done without opening or evacuating the appliance: “the test must be performed after the conclusion of the repairs and before any additional refrigerant is added” (84.106(e)(1)(i)).
  • Repairs that need evacuation of the appliance or part of it: “the test must be performed before adding any refrigerant to the refrigerant-containing appliance” (84.106(e)(1)(ii)).
  • If the test shows the repair did not work, the owner or operator “may conduct as many additional repairs and initial verification tests as needed within the applicable time period” (84.106(e)(1)(iii)).

The follow-up test

“Where it is unsafe to be present or otherwise impossible to conduct a follow-up verification test when the system is operating at normal operating characteristics and conditions, the verification test must, where practicable, be conducted prior to the system returning to normal operating characteristics and conditions.”

84.106(e)(2)

If the follow-up test shows the repair failed, the owner or operator “may conduct as many additional repairs and verification tests as needed to bring the refrigerant-containing appliance below the leak rate within the applicable time period and to verify the repairs” (84.106(e)(2)(i)).

When a repair is presumed successful

“Repairs of leaks must be documented by both an initial and a follow-up verification test or tests.”

84.106(d)(2)

The same paragraph says repairs “will be presumed to be successful if, over the 12-month period after the date of a successful follow-up verification test, there is no further refrigerant addition or if the leak inspections required under paragraph (g) and/or automatic leak detection systems required by § 84.108 do not find any leaks in the appliance.” Leak inspection frequency is counted “after the date of a successful follow-up verification test” in 84.106(g)(1). The leak rate math is on the leak rate page.

The records the rule names

“Owners or operators must maintain records of the dates and results of all initial and follow-up verification tests. Records must include the location of the refrigerant-containing appliance, the date(s) of the verification tests, the location(s) of all repaired leaks that were tested, the type(s) of verification test(s) used, and the results of those tests.”

84.106(m)(7)

The same paragraph adds that the certified technicians doing the tests “must, upon conclusion of that service, provide the owner or operator of the appliance with documentation that meets these requirements.” As columns: the log template. The 30-day repair window itself: the requirements, quoted.

Questions to ask of your own file: questions, not advice

  • For the last repaired leak, can you find a dated initial test and a dated follow-up test, each tied to the leak location?
  • Does each test record say which type of test was used and what the result was?
  • Is the gap between the two tests written down, so you can see it against the 10 days in the rule text?
  • Did the technician hand you the documentation when the service ended?

The rule text does not tell us whether a specific appliance is covered. EPA and your counsel can answer that. Book a walkthrough call for the concept, not for advice.

Questions

What is an initial verification test for a refrigerant leak repair?

Section 84.106(e)(1) says it must demonstrate that the adjustments or alterations made to the appliance have held, and be performed within 30 days (120 if an industrial process shutdown is required) of the appliance exceeding the applicable leak rate, unless granted additional time (as of Nov 8, 2026).

What is a follow-up verification test?

Section 84.106(e)(2) says it must be performed within 10 days of the successful initial test, or of the appliance reaching normal operating characteristics and conditions if it was evacuated for the repair, and must demonstrate that the leaks where repair was attempted are repaired (as of Nov 8, 2026).

Does the rule say which test method to use?

The quoted text of 84.106(e) does not name a method. The records paragraph, 84.106(m)(7), asks for the type of verification test used and its results.

Does this page tell me whether the rule applies to my appliance?

No. EPA and your counsel can answer for your appliances.